The Highway 55 overpass (bridge) is on schedule according to Micky Klasen, project supervisor. Currently cars are detoured around the overpass, located between Kimball and Watkins, while the replacement is being accomplished. The substucture units (pile driving, two piers and two abutments) are complete for the new bridge. The beams for the new bridge are scheduled to be placed on Monday, Aug. 8. The superstructure units (deck, railing, overlay and approach panel) will be constructed afterwards.